project logo

The Tucson Department of Transportation (TDOT) is the lead agency on this multi-agency funded project.

The Regional Transportation Authority (RTA) Plan includes project #17 as: widen Broadway to 6 travel lanes, plus 2 dedicated bus lanes; bike lanes; and sidewalks.

As part of the current Planning & Design Phase work, this project scope is being reviewed, along with other possible roadway configuration alternatives.

At the end of this Planning & Design Phase, a Citizens Task Force-recommended, community-supported Design Concept Report and initial (15%) construction plans will be completed.

This Planning & Design Phase is estimated to conclude in 2015.  A Final Design Phase will follow, which will bring all construction plans to 100% complete and construction-ready.

Construction is not anticipated until 2016.

 

Public Meetings

The next two public meetings of the Broadway Citizens Task Force will be held in the same week:

Tuesday, May 21, 2013, 5:30 pm (agenda)
AND
Thursday, May 23, 2013, 5:30 pm (agenda)

2800 E. Broadway, Child & Family Resources

These meetings will primarily focus on:

Draft Performance Measures for Broadway and
Developing Initial Cross-Section Concepts
(Or view the Entire Packet of meeting materials)

View the Broadway Citizens Task Force's page on the City Clerk's web site.  To view materials from past meetings, check the Citizens Task Force page.

 

Confirmed CTF Meetings for 2013: 
Additional meeting dates are in the process of being identified and will be added as soon as they are available.

Meeting Type                                  Date                     
CTF Meeting                           May 21, 2013
CTF Meeting                           May 23, 2013
CTF Meeting                           May 30, 2013
CTF Meeting                           June 20, 2013

 

Latest Additions to this Project Web Site

 

Additional Project Information

Cost

The total budget for the Broadway Road Widening from Euclid to Country Club is $71,347,000.  Funding of the project will come from Regional Transportation Authority (approximately $42 million), Pima County Transportation Bonds (approximately $25 million), the City of Tucson (approximately $3 million), and regional funds from the Pima Association of Governments (approximately $1 million).

Schedule

The project launched the Planning & Design Phase of the project on June 20, 2012, which will take almost 2 years to complete.  This phase provides the most public input and involvement.  Utilizing public participation and collaboration with affected neighbors, businesses, stakeholders, and other interests affected by this project, a Design Concept Report will be developed that will guide the final design and construction.  A Citizens Task Force has been appointed and will meet regularly with the proejct team to develop this Design Concept Report.

The Design Concept Report will evaluate urban design concepts and roadway design, and will include:

  • Traffic flow and mobility

  • Safety, connectivity and facilities for bicycle and pedestrians

  • Enhancing bus transit capability

  • Protection of neighborhoods and historic character

  • Sustainability; greening of an urban boulevard; landscape design

  • Land use redevelopment opportunities; transit oriented development

  • Future light rail planning

  • Gateway planning and development

Based on the Design Concept Report, a Value Engineering Analysis can be conducted to develop a more tailored budget for the improvements to be constructed.  The Final Design phase will begin in 2015 and should take approximately 1 year.  Land use recommendations will be addressed, as appropriate to the project.   Final construction drawings will be created.  Right-of-Way acquisition can also be finalized. Utility relocations are expected in 2015 or 2016.

Roadway construction is not anticipated until 2016.