St. Mary’s Road/Sixth Street I-10 to Church Avenue Roadway Improvement Project

On Thursday, January 16, 2014, the contractor will switch traffic control from the temporary traffic signals to the new permanent traffic signals at the Granada Avenue and St. Mary’s Road intersection. During the work and until the new traffic signals are in operation, Tucson Police officers will direct traffic through the intersection. The work is scheduled to begin at 9 a.m. and be complete by 3 p.m.

test page 2

New page test 2

Park Avenue Enhancements, Speedway to Ft. Lowell

PROJECT SCOPE

This project consists of installing sidewalk improvements along the roadway on Park Avenue between Speedway and Ft. Lowell. Improvements will include installing additional bike path where needed, earthen type pedestrian improvements, and landscaping improvements.

NEW -- CONSTRUCTION UPDATES:

January 2014 - 60% design under review.

Traffic Signal Control Changes at Houghton Road and Broadway Intersection

On Thursday, January 9, 2014, beginning at 9 a.m., the City of Tucson Department of Transportation (TDOT) and Borderland Construction will switch traffic control from the old traffic signals to the new temporary traffic signals at the Houghton Road and Broadway intersection. During the work and until the new temporary traffic signals are in operation, Tucson Police officers will direct traffic through the intersection. The switch-over is scheduled to be complete by 4 p.m. the same day.