BROADWAY WORK MOVES TO NIGHTTIME

To lessen the congestion on the traveling public and to stay on schedule, Southern Arizona Paving and Construction Co, under contract with the City of Tucson Department of Transportation (TDOT), will move the crack seal work taking place on Broadway to night hours.  Crack sealing work will take place between 7 p.m. and 5 a.m., Monday through Thursday.

The work on Broadway, from Country Club Road to Wilmot Road is still scheduled to be complete by Friday, March 7, 2014.

During this work, travel lane restrictions will be in place, however at least two lanes of travel will be maintained in both directions.

Business and residential access will be maintained at all times during the project.  The traveling public can expect delays when driving in the work area.  Please obey all traffic control signs and watch for construction personnel and equipment in the work area.

The Road Recovery Program is funded by voter-approved bonds. All proceeds from the bonds will be used to restore and resurface City streets through Fiscal Year 2018.  A Bond Oversight Commission composed of citizen volunteers is working to ensure that all bond funds are expended solely for the purpose of repairing city streets. 

More information on the Road Recovery Program can be found at www.tucsonaz.gov/streetbonds or by calling (520) 837-4056. Follow @TucsonRoadRecovery on twitter.